When is Chinese New Year and why does the date move?
Chinese New Year, the Spring Festival, follows the Chinese lunar calendar rather than the Gregorian one, so the date shifts every year. In practice it falls somewhere between late January and mid-February, and two consecutive years can be three weeks or more apart. That alone is reason enough not to copy last year's schedule: the production window you relied on may have moved a fortnight earlier.
The working rule is to confirm next year's actual date at the start of each year and rebuild your plan backwards from it. And do not lean on a factory promising to "work through the holiday" — the sales office may reply to email, but the production line, the sub-suppliers and domestic transport will not be running.
How many weeks do factories really stop?
The official public holiday is far shorter than the industrial shutdown. Real lost capacity usually runs two to four weeks, sometimes longer at smaller plants, for three reasons:
- Before the holiday: many workers travel to distant home provinces days before the official start, so output tapers off gradually.
- During the holiday: a near-total stop covering the factory, raw material suppliers, domestic trucking and customs handling.
- After the holiday: the restart is gradual, not instant. A share of the workforce never returns and takes work in another city, so the plant needs weeks to reach full capacity.
This is why an importer who plans around "one week off" is surprised by a month of delay. A safe planning range is three to five weeks of lost capacity around the holiday, adjusted for factory size and your own history with them.
When should I place the pre-holiday order?
Plan backwards from the date the goods must be in your warehouse, not forwards from today. Working in reverse:
- The date you need stock in the warehouse or your selling season starts.
- Minus transit and clearance: ocean freight from South China to the Gulf typically runs around 18 to 30 days depending on port and service, plus clearance and inland delivery days.
- Minus booking and handling: roughly a week from cartons sealed to vessel departure in normal conditions, longer in peak season.
- Minus pre-shipment inspection and time to close any findings: 5 to 10 days.
- Minus production time: often 25 to 45 days for standard goods, longer for custom items or anything needing tooling.
- Minus sampling and approval: two weeks to a month across first sample, review, revision and final sign-off.
The typical result: issue the purchase order and pay the deposit at least three to four months before the holiday if you want the goods in hand beforehand. If you can accept post-holiday delivery, assume production will not resume seriously until about two weeks after the official return date.
What does the annual China import calendar look like?
| Month | What happens in factories and ports | What you should do |
|---|---|---|
| January | Final rush before the holiday, new orders declined, congested ports | Close out inspections and shipments; do not start a new product now |
| February | Chinese New Year usually falls here or in late January; near-total shutdown | Live off safety stock; use the time for planning and negotiation |
| March | Gradual restart, labour shortages, changed lines and supervisors | Inspect the first batch strictly; lock annual pricing |
| April | Canton Fair usually starts mid-month; factories busy with visitors | Meet suppliers, develop new products, expect slower replies |
| May | Labour Day break in the first days, then stable output | An excellent window for production and sampling |
| June | Stable production; freight rates begin drifting upward | Book Q3 shipments early |
| July | Ocean peak season toward Western markets begins | Close year-end orders; fix freight rates |
| August | Peak volumes, space shortages, typhoon season can close southern ports | Add a two-week buffer to any critical shipment |
| September | Pre-Golden Week rush, heavy pressure on production and ports | Get shipments out before month end |
| October | Golden Week at the start, then the autumn Canton Fair | Schedule nothing for the first week; start the CNY plan |
| November | Last practical window to start pre-holiday production; 11.11 strains domestic logistics | Issue purchase orders and pay deposits |
| December | Factories full and rushing, so quality risk rises | Increase inspection; book containers early |
These dates are approximate. Chinese New Year moves each year, and fair and public holiday dates are announced annually. Confirm the real dates before you lock a schedule.
Which other seasons squeeze the schedule?
- Golden Week (early October): a national holiday of roughly a week. Lighter than CNY, but easily enough to delay a critical shipment.
- Labour Day (early May): a short break of a few days, usually affecting domestic transport more than production.
- Canton Fair (April and October): excellent for meeting suppliers, but sales teams are away from their desks and replies and samples slow down.
- Ocean peak season (mid-summer into autumn): container demand rises ahead of Western selling seasons, so rates climb, space tightens and rolled bookings become more likely.
- Typhoon season: southern ports can close for days in late summer. Nobody controls it, so it belongs in your buffer rather than your excuses.
What are the hidden risks after factories return?
The bigger post-holiday risk is not delay but quality. The causes repeat every year: high workforce turnover puts untrained operators on unfamiliar lines, supervisors change, raw material comes from a substitute supplier because the original has not restarted, and everyone is under pressure to recover lost time. The result is that the first batch after the holiday is the highest-risk production run of the year.
Practically: treat that batch as a new product launch rather than a repeat order. Ask for a production sample before the full run, inspect during manufacturing rather than only at the end, and lock the specification in writing before the shutdown so it is not renegotiated with a new team. Expect a price-increase conversation on return, justified by wages and materials; agreeing annual pricing before the break removes that round entirely.
Annual planning checklist
- Have you confirmed next year's actual Chinese New Year date?
- Did you build the schedule backwards from the need-by date rather than forwards from today?
- Have you raised safety stock on your fastest-moving SKUs before the shutdown?
- Are annual prices and specifications locked in writing before the factory stops?
- Have you booked freight space early for peak months?
- Is enhanced inspection scheduled for the first post-holiday batch?
- Do you have a qualified alternate supplier for your top two SKUs?
- Have you added a two-week buffer to any shipment tied to a selling season?
Practical takeaway
Importing from China is not a steady year-round activity; it is a calendar with distinct seasons. Chinese New Year is the largest event: the date moves annually, real lost capacity runs two to four weeks, and the first batch after the break carries the highest quality risk of the year. Importers who plan backwards three to four months buy at normal prices with time to spare; those who wait buy at peak rates with no schedule flexibility left.
At ALSHUMUL we build an annual calendar with the client that ties purchase order dates to inspection and ocean booking dates, and we deliberately tighten inspection on the first post-holiday batch, because most first-quarter problems are actually created the previous November.